The Matanuska-Susitna Borough received funds to design and construct the Machen Road and Museum Drive extensions in 2008. In May 2009, Lounsbury received the go-ahead to begin design and produce bid-ready plans by late 2010. Construction could begin as early as 2011.

Machen Schedule Graphic


Begin project - May 2009
Environmental - May 2009 through January 2010
Surveying - June 2009 through August 2009
Geotechnical Investigation - August 2009 (10 days)
Traffic and Safety Analysis - June 2009 through July 2009
Design Study Report - September 2009 through mid-December 2009
Right of Way Mapping - August 2009 through April 2010
Right of Way Acquisition - April 2010 through beginning of construction 2011
Utilities - September 2009 through November 2009
Plans, Specification and Estimates - August 2009 through September 2010
Bidding & Construction Contract Award - September 2010 through beginning of construction 2014
Construction is anticipated in 2014
Public Involvement - May 2009 through beginning of construction 2011