The project has been put on temporary hold until the Machen Road Extension is complete and the remaining budget determined
The schedule below was the previous anticipated schedule.

Museum Schedule


Begin project - May 2009
Environmental - May 2009 through February 2010
Surveying - June 2009 through July 2009
Geotechnical Investigation - July 2009 (15 days)
Traffic and Safety Analysis - June 2009 through July 2009
Design Study Report - September 2009 through mid-December 2009
Right of Way Mapping - August 2009 through April 2010
Right of Way Acquisition - April 2010 through end of design September 2012
Utilities - September 2009 through September 2012
Plans, Specification and Estimates - August 2009 through September 2012
Bidding & Construction Contract Award - September 2012 through beginning of construction 2013
Construction is anticipated in 2013
Public Involvement - May 2009 through beginning of construction 2013